UFC 3-430-02FA 15 May 2003 Including change 1, December 2007 UNIFIED FACILITIES CRITERIA (UFC) CENTRAL STEAM BOILER PLANTS APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED INACTIVE UFC 3-430-02FA 15 May 2003 Including change 1, December 2007 1 UNIFIED FACILITIES CRITERIA (UFC) CENTRAL STEAM BOILER PLANTS Any copyrighted material included in this UFC is identified at its point of use. Use of the copyrighted material apart from this UFC must have the permission of the copyright holder. U.S. ARMY CORPS OF ENGINEERS (Preparing Activity) NAVAL FACILITIES ENGINEERING COMMAND AIR FORCE CIVIL ENGINEER SUPPORT AGENCY Record of Changes (changes are indicated by \1\ ... /1/) Change No. Date Location 1 Dec 2007 Pages 8-10 & 8-11, Chapter 8, Para 8-4b(2) This UFC supersedes TM 5-810-15, dated 1 Augu
10 & 8-11, Chapter 8, Para 8-4b(2) This UFC supersedes TM 5-810-15, dated 1 August 1995. The format of this UFC does not conform to UFC 1-300-01; however, the format will be adjusted to conform at the next revision. The body of this UFC is a document of a different number. INACTIVE UFC 3-430-02FA 15 May 2003 Including change 1, December 2007 2 FOREWORD \1\ The Unified Facilities Criteria (UFC) system is prescribed by MIL-STD 3007 and provides planning, design, construction, sustainment, restoration, and modernization criteria, and applies to the Military Departments, the Defense Agencies, and the DoD Field Activities in accordance with USD(AT&L) Memorandum dated 29 May 2002. UFC will be used for all DoD projects and work for other customers where appropriate. All construction outside of th
systems, with the facility being self-powered during operations except in emergencies and start up conditions. Provide natural gas supplementation for boiler system start up and maintenance heating. 5-2.1.1 General Development Plan. Prepare a general development plan for the project life cycle. Include the following phases as a minimum: feasibility, design, construction, operation, and decommissioning. 5-2.1.2 Site Planning and Development. Use UFC 3-240-05A, Chapter 2 (for Army), and UFC 3-430-02FA, Chapter 2 (for Army/Air Force), for general site planning and development. Note: Navy to use UFC 3- UFC 3-540-08 23 January 2017 35 240-05A and UFC 3-430-02FA as reference only. Follow local shore installations planning guidance. Consider Table 5-1 during site planning evaluation: Table 5-1 Pl
UFC 3-240-03N (MIL-HDBK-1138), Wastewater Treatment System Operation and Maintenance Augmenting Handbook, 16 January 2004 UFC 3-240-13FN, Industrial Water Treatment Operation and Maintenance, 25 May 2005 UFC 3-420-01, Plumbing Systems, 23 June 2010 UFC 3-430-09, Exterior Mechanical Utility Distribution, 16 January 2004 UFC 3-460-01, Design: Petroleum Fuel Facilities, 16 August 2010 UFC 3-460-03, Maintenance of Petroleum Systems, 21 January 2003 UFC 3-601-02, Operation and Maintenance: Inspection, Testing, and Maintenance of Fire Protection Systems, 8 September 2010 UFC 4-020-01, DoD Security Engineering Facilities Planning Manual, 11 September 2008 UFC 4-020-02FA, Security Engineering: Concept Design, 1 March 2005 UFC 4-020-03FA, Security Engineering: Final Design, 1 March 2005 UFGS 33 51
nterior Design UFC 3-190-06, Protective Coatings and Paints UFC 3-201-01, Civil Engineering UFC 3-201-02, Landscape Architecture UFC 3-210-10, Low Impact Development UFC 3-220-01, Geotechnical Engineering UFC 3-230-01, Water Storage and Distribution UFC 3-230-03, Water Treatment UFC 3-240-01, Wastewater Collection and Treatment UFC 3-301-01, Structural Engineering UFC 3-301-02, Design of Risk Category V Structures, National Strategic Military Assets UFC 3-401-01, Mechanical Engineering UFC 3-410-01, Heating, Ventilating, and Air Conditioning Systems CANCELLED UFC 1-200-01 01 September 2022 Change 4, 17 December 2024 71 UFC 3-420-01, Plumbing Systems UFC 3-430-05, Natural Gas and Liquefied Petroleum Gas (LPG) Distribution Pipelines UFC 3-460-01, Design: Petroleum Fuel Facilities UFC 3-490-0
th the shore; a wharf is used for berthing or mooring vessels. May also be as above, except with continuous connection to shore. UFC 4-150-02 12 November 2020 201 REFERENCES F-1 GOVERNMENT PUBLICATIONS UNIFIED FACILITIES CRITERIA (UFC) https://www.wbdg.org/ffc/dod UFC 1-200-01, DoD Building Code UFC 3-190-06, Protective Coatings and Paints UFC 3-220-10N, Soil Mechanics UFC 3-230-01, Water Storage and Distribution UFC 3-400-02, Design: Engineering Weather Data UFC 3-430-09, Exterior Mechanical Utility Distribution UFC 3-460-01, Design: Petroleum Fuel Facilities UFC 3-501-01, Electrical Engineering UFC 3-520-01, Interior Electrical Systems UFC 3-550-01, Exterior Electrical Power Distribution UFC 3-560-01, Electrical Safety Operation and Maintenance UFC 3-570-01, Cathodic Protection UFC 3-575
e UFCs for all aspects of design, including but not limited to: UFC 1-200-01, DoD Building Code UFC 1-200-02, High Performance and Sustainable Building Requirements UFC 2-100-01, Installation Master Planning UFC 3-130-01, Arctic and Subarctic Engineering UFC 3-130-02, Arctic and Subarctic Site Assessment and Selection UFC 3-130-03, Arctic and Subarctic Foundations for Freezing and Thawing Conditions UFC 3-130-04, Arctic and Subarctic Buildings UFC 3-201-01, Civil Engineering UFC 3-230-01, Water Storage, Distribution, and Treatment UFC 3-230-02, Operation and Maintenance: Water Supply Systems UFC 3-240-01, Wastewater Collection and Treatment UFC 3-410-02, Direct Digital Control for HVAC and Other Building Control Systems UFC 3-430-05, Natural Gas and Liquified Petroleum Gas (LPG) Distributi
Utility Monitoring & Control System (UMCS) Front End and Integration UFC 3-420-02 Compressed Air UFC 3-440-01 Facility-Scale Renewable Energy Systems Fueling Systems UFC 3-460-01 Design: Petroleum Fuel Facilities UFC 3-460-03 Petroleum Fuel Systems Maintenance MO-230 M&O of Petroleum Fuel Facilities UFC 3-410-04 Industrial Ventilation UFC 3-430-09 Exterior Mechanical Utility Distribution Central Plants UFC 3-430-11 Boiler Plant Instrumentation and Control Systems UFC 3-490-06 Elevators UFC 4-826-10 Design: Refrigeration Systems for Cold Storage UFC 3-430-01FA Heating & Cooling Distribution Systems CANCELLED UFC 3-401-01 28 July 2025 Change 2, 14 May 2026 3 CHAPTER 2 TECHNICAL REQUIREMENTS 2-1 DOCUMENTATION REQUIREMENTS Comply with the design analysis and drawing requirements in the UFC 3-4