Plain English, any career field. Answers cite the AF pub + paragraph, your command's supplement, and the federal (OSHA/CFR) standard behind it — with the official PDF one click away.
NFPA text is copyrighted — we cite and link the official free-access viewer, never reproduce it.
UFC 3-210-10 28 August 2023 UNIFIED FACILITIES CRITERIA (UFC) APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED LOW IMPACT DEVELOPMENT CANCELLED UFC 3-210-10 28 August 2023 This Page Intentionally Left Blank CANCELLED UFC 3-210-10 28 August 2023 UNIFIED FACILITIES CRITERIA (UFC) LOW IMPACT DEVELOPMENT Any copyrighted material included in this UFC is identified at its point of use. Use of the copyrighted material apart from this UFC must have the permission of the copyright holder. Indicate the preparing activity beside the Service responsible for preparing the document. U.S. ARMY CORPS OF ENGINEERS NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND (Preparing Activity) AIR FORCE CIVIL ENGINEER CENTER Record of Changes (changes are indicated by \1\ ... /1/) Change No. Date Location This UFC sup
ges (changes are indicated by \1\ ... /1/) Change No. Date Location This UFC supersedes UFC 3-210-10, dated June 2015. CANCELLED UFC 3-210-10 28 August 2023 This Page Intentionally Left Blank CANCELLED UFC 3-210-10 28 August 2023 FOREWORD The Unified Facilities Criteria (UFC) system is prescribed by MIL-STD 3007 and provides planning, design, construction, sustainment, restoration, and modernization criteria, and applies to the Military Departments, the Defense Agencies, and the DoD Field Activities in accordance with USD (AT&L) Memorandum dated 29 May 2002. UFC will be used for all DoD projects and work for other customers where appropriate. All construction outside of the United States its territories, and possessions is also governed by Status of Forces Agreements (SOFA), Host Nation Fu
int where it falls. The LID features are distributed small-scale controls that closely mimic the hydrological behavior of the pre-project sites for a design storm event. CANCELLED UFC 3-210-10 28 August 2023 63 Pre-Development: pre-project conditions that exist at the beginning of design. Where phased development occurs, the existing conditions at the time prior to the first phase being submitted will establish pre-development conditions. CANCELLED UFC 3-210-10 28 August 2023 64 This Page Intentionally Left Blank CANCELLED UFC 3-210-10 28 August 2023 65 APPENDIX C REFERENCES DEPARTMENT OF DEFENSE DODI 4165.14 Real Property Inventory and Forecasting ENVIRONMENTAL PROTECTION AGENCY EPA 841-B-09-001, Technical Guidance on Implementing the Stormwater Runoff Requirements for Federal Projects un
. (T-1) Programmers must ensure all projects adhere to UFC 1-200-02, High Performance and Sustainable Building Requirements; UFC 2-100-01, Installation Master Planning; UFC 3-210-10, Low Impact Development; and the most current DoD policy and DAF Sustainable Design and Development (SDD) implementing guidance. (T-1) When applicable, programmers must ensure programming documents include the cost associated with sustainable design elements necessary to achieve sustainable design guidance compliance and most current UFC 1-200-02. (T-0) DAF SDD implementing guidance, including mandatory third-party certification and mandatory Federal compliance tracking and reporting is found in UFC 1-200-02, and is maintained by AFCEC at https://www.wbdg.org/dod/sustainability. 2.7.15. Accessibility. Programme
onal parking should be considered for shift changes. Specific criteria are given in UFC 3-210-02, POV Site Circulation and Parking. 3-10.2 Pavement Design. Exterior paved areas include aircraft, pedestrian and vehicle access and parking. Vehicle access and parking should be in accordance with UFC 3-250-01FA, Pavement Design for Roads, Streets, Walks, and Open Storage Areas. UFC 4-133-01 19 April 2016 Change 2, 25 June 2019 60 3-10.3 Site Utilities. Reference UFC 3-210-01A, Area Planning, Site Planning and Design; UFC 3-210-06A, Site Planning and Design; and UFC 3-230-04A, Water Distribution. 3-10.4 Site Lighting. Orient exterior fixtures to minimize glare on ramps and taxiways. Use full cut-off type fixtures. Refer to UFC 3-260-01, Airfield and Heliport Planning and Design for clearance re
gineering, and applicable requirements of the local regulatory agency with jurisdiction over the installation; UFC 3-210-10, Low Impact Development; and the criteria in this DAFMAN. (T-0) When there is a conflict among criteria, installations will follow the most stringent. Other important construction-related stormwater references include UFC 1-200-02, High Performance and Sustainable Building Requirements, and EPA 841-B-09-001, Technical Guidance on Implementing the Stormwater Runoff Requirements for Federal Projects Under Section 438 of the Energy Independence and Security Act. 6.2. Operation and Maintenance and Compliance. The BCE must operate and maintain stormwater facilities within applicable permit limits and according to relevant guidance in the applicable Civil Engineering Playbo
applies when there are no international agreements in place. Therefore, in foreign countries this UFC will be used for DoD projects to the extent that it is allowed by and does not conflict with the applicable international agreements. 1-4 GENERAL BUILDING REQUIREMENTS. Comply with UFC 1-200-01, DoD Building Code. UFC 1-200-01 provides applicability of model building codes and government unique criteria for typical design disciplines and building systems, as well as for accessibility, antiterrorism, security, high performance and sustainability requirements, and safety. Use this UFC in addition to UFC 1-200-01 and the UFCs and government criteria referenced therein. 1-4.1 Low Impact Development. Use UFC 3-210-10 for Low Impact Development (LID) criteria. UFC 3-210-10 was developed to compl
1-02, Landscape Architecture UFC 3-210-02, POV Site Circulation and Parking UFC 3-210-10, Low Impact Development UFC 3-400-01, Energy Conservation UFC 3-410-01FA, Heating, Ventilating, and Air Conditioning UFC 3-450-01, Noise and Vibration Control UFC 3-520-01, Interior Electrical Systems UFC 3-530-01, Design: Interior and Exterior Lighting and Controls UFC 3-600-01, Fire Protection Engineering for Facilities UFC 4-010-01, DoD Minimum Antiterrorism Standards for Buildings UFC 4-720-01 13 February 2012 100 APPENDIX B BEST PRACTICES B-1 INTRODUCTION. The following material identifies background information and other current, good design practices for LFs. The designer is expected to review and interpret this guidance and apply the information according to the needs of the project. B-2 PROJEC
⚠ Unofficial. Answers come from indexed publication text and may be incomplete or out of date. Your MAJCOM/unit supplement may be stricter. Always verify against the official publication before acting, citing, or writing a finding.
New and updated AFIs, supplements, and OSHA cross-references as we index them — straight to your inbox.